Production Flow

Installation Steps

  1. Engineering Line Measurement
  2. Wall & Column Rebar Binding
  3. Specialty Reservation Preparation
  4. Wall or Column Panel Installation
  5. Flat tie and PVC Sleeve Installation
  6. Beam Panel Installation
  7. Deck Panel
  8. Staircase Formwork
  9. Drop Frame Installation
  10. Formwork Inspection
  11. Concreting of Structure
  12. Formwork Dismantle
  13. Move to the next assembly